Project construction began in early May, 2009. This followed a year of data collection,
design and community involvement. The following dates summarize construction activities for the 2009
construction season. Keep in Mind dates and activities may change with weather, unknown and
unanticipated site elements. Contact David Prusak at 575-5186 for the most recent information.
April 2009
- TAM selected to perform construction
May 2009
- TAM Construction, Inc.
letter sent to homeowners regarding project.
- Begin work on the Booster Station and water mains starting on W. 84th Avenue from Endicott Street
to Jade Street and on Jade Street from W. 84th to W. 88th Avenue continue work throughout the summer.
- Begin gas line relocation on W. 84th Avenue
- Begin gas line relocation on Jade Street
June 2009
- Begin gas line relocation on W. 80th Avenue
- Begin work on Jade Street Check Valve
July 2009
- Begin paving Jade Street, W. 84th Avenue, and Booster Station
- Begin work on sewer main on W. 80th Avenue
- Landscape Booster Station, W. 84th Avenue, and Jade Street
August 2009
- Pave W. 80th Avenue
- Begin work on Jade Street Check Valve
- Landscape W. 80th Avenue