Both the water and sewer mains are important to not only improve basic needs of the immediate neighborhood, but to serve as the backbone for future water and sewer laterals. The proposed water extension is approximately 3,400 linear feet of 8-inch water main that will connect the existing system at Jade and 88th Avenue, follow Jade to 84th Avenue, turn west along 84th Avenue to Sand Lake, then north along Sand Lake to 80th Avenue. Two booster stations may be needed to maintain operating pressure, one at Sand Lake Road and 84th Avenue and one at the corner of Jade Street and 88th Avenue.
The sewer extension includes approximately 2,500 linear feet of pipe that will be constructed beneath 80th Avenue, within the right-of-way, from Sand Lake Road to Sand Lake Canal.