Design Study: |
Complete |
Surveying: |
Complete |
Design: |
65% Design Draft submitted and on hold pending additional field work. |
Existing Pipe Condition Assessment: |
Ongoing. Two isolation valves were installed in May 2010 and a physical condition assessment of the existing 2 inch water distribution pipe was conducted. Recommendations from this investigation are forthcoming and will establish the future time line of this project. |
Public Involvement: |
A newsletter update will be issued upon completion of the foregoing pipe condition assessment. |
Construction: |
Estimated 2011 or later. |